This project is live

The 2010 Landcare Project called McKinnon Creek Crossing involving our landcare members Geoff and Penelope Slocombe, in consultation with the Glenelg Hokins CMA including advice from the GHCMA engineer Tim Tutt.

 The
project is on the South side of the Glenelg Highway approx 10kms from Hamilton.   
Spiny
Rush was removed from McKinnon Creek within a Billabong which was made bigger.
Filling
was put across McKinnon Creek with a center pipe to allow water to flow through.
This filling was cemented in with a dip in  the centre of the  crossing to allow
water to flow over the crossing. The crossing is 6meters.
Billabong
already has native species in its waters.
More photos can be seen in the Photo Album